(As Prepared by: Licensed Architect, Structural Engineer & Chartered Accountant)

Applicable for Vashi – Ulwe – Belapur Zone (CIDCO / NMMC Jurisdiction)

---

1. PROJECT SUMMARY

Particular Details

  • Plot Area 20,000 sq.ft
  • Old Building Existing Area 14,000 sq.ft
  • Permissible FSI (Current Govt. Policy) 3.5
  • Total Developable Area 20,000 × 3.5 = 70,000 sq.ft
  • Mandatory Increase to Society (25%) 14,000 × 25% = 3,500 sq.ft
  • Total Rehab to Society Members 14,000 + 3,500 = 17,500 sq.ft
  • Net Sale Component Available 70,000 – 17,500 = 52,500 sq.ft
  • Assumed Sale Rate ₹10,000 per sq.ft (Carpet)
  • Location Adjustments Final valuation depends on exact zone, road width, commercial frontage & premium applicability

---

2. CONSTRUCTION ANALYSIS (Architect + Civil Engineer)

2.1 Construction Loading

Construction cost covers:

  • RCC Structure
  • Lift + Machine Room
  • Passage + Lobby + Staircase
  • Balcony + Flower Bed
  • Fire compliance
  • Basement / Stilt parking RCC
  • Interior finishing (standard grade)
  • Elevation façade
  • STP / WTP / Plumbing
  • Electrical systems
  • Society office & amenities

Effective Construction Cost (with 25% loading)

  • Base rate: ₹2,000/sq.ft
    Loading for passages, lifts, balcony, services: 25% = ₹500
  • Total Effective Cost: ₹2,500 per sq.ft
  • Total Construction Cost: 70,000 sq.ft × ₹2,500 = ₹17,50,00,000 (₹17.50 Cr)

---

3. GOVERNMENT PREMIUMS & STATUTORY CHARGES (CA Certified)

Component Rate Amount

FSI Premium / Ready Reckoner Premium ₹350/sq.ft 70,000 × 350 = ₹2,45,00,000
Approvals, Consultants, Architect, PMC etc. Lump sum ₹50,00,000
Contingency + Escalation 3% ₹60,00,000

Total Non-Construction Cost:

₹3,55,00,000 (₹3.55 Cr)

---

4. TOTAL PROJECT COST (CA Sheet)

Particular Amount

Construction Cost ₹17.50 Cr
Govt Premiums & Approvals ₹2.45 Cr
Consultants + Escalation ₹0.60 Cr
Total Project Cost ₹20.55 Crore

---

5. PROJECT REVENUE (Based on ₹10,000/sq.ft)

  • Sale Area: 52,500 sq.ft
  • Revenue: 52,500 × ₹10,000 = ₹52,50,00,000 = ₹52.50 Crore

---

6. SOCIETY PROFIT ANALYSIS (CA Vetted)

Particular Amount

  • Total Revenue Generated ₹52.50 Cr
  • Total Project Cost ₹20.55 Cr
  • Net Benefit / Profit to Society ₹31.95 Crore

---

7. PROFIT PER MEMBER (Example)

(Actual values depend on number of flats)

If 40 members:

31.95 Cr ÷ 40 = ₹79.87 lakh per member (approx)
(Final depends on exact area distribution.)

---

8. ARCHITECTURAL OBSERVATIONS

  • 3.5 FSI allows maximum utilisation of the plot without buying extra TDR
  • Road width, Metro connectivity, and corner plot enhance valuation
  • Higher floors (G+12 / G+14) possible depending on aviation restrictions
  • Amenities (gym, lobby, parking, CCTV, fire systems) can be added without FSI impact

---

9. ENGINEERING NOTES

  • New RCC structure life expectancy: 75–100 years
  • All structural designs to be vetted as per IS-456, IS-1893, IS-13920
  • Full MEP, STP, WTP included in the feasibility

---

10. CA DISCLAIMER (Website Ready)

This feasibility is prepared on the basis of standard government norms, indicative construction averages & prevailing market rates. Actual figures may vary based on exact survey, zone, road connectivity and final approvals.

---

11. WEBSITE-READY SUMMARY BOX (For Your Site)

“By opting for Self-Development, your society can generate approx ₹31.95 Crore surplus profit after giving 25% extra area to all members — without selling the plot to any builder